Cut → Weld → Paint → Inspect → Pack. Backward fails; forward lands ~Tue 2026-08-11 11:00.
Required
Fri 07 Aug · 16:00
Planned completion
Not scheduled yet
Earliest feasible
Not scheduled yet
WO-1004Marine hatch frameQty 8
plannedShow on board
- 10Cut platecuttingWork centre: CuttingDuration: 4hMaterial: Mild steel plate 10mm
- 20Weld frameweldingWork centre: WeldingDuration: 10h
- 30PaintpaintingWork centre: PaintingDuration: 8hMaterial: Marine-grade paint
- 40InspectioninspectionWork centre: InspectionDuration: 2h
- 50PackingpackingWork centre: PackingDuration: 2h