SO-1008

·Harbourline AssembliesStandardNet 30Show all on board

Clean feasible order — welding + inspection subassembly.

Required
Fri 14 Aug · 16:00
Planned completion
Not scheduled yet
Earliest feasible
Not scheduled yet
WO-1008Tube subassemblyQty 25
  1. 10
    Weld tube subassemblywelding
    Work centre: WeldingDuration: 4hMaterial: Stainless tube 304
  2. 20
    Inspectioninspection
    Work centre: InspectionDuration: 1h
WO-1009Fastener kit packQty 25
  1. 10
    Pack fastener kitspacking
    Work centre: PackingDuration: 3hMaterial: Fastener kit assorted